Port Authority
January - May 2026
Pilbara Region, WA
GTE's client for this project operates a port facility in the Pilbara. A key part of the port's bulk materials handling operation is a rail mounted hopper train – consisting of 3 hoppers and a motor control centre mounted on a mobile assembly.
The existing ABB variable speed drives (VSDs) on the hopper train had reached the end of their service life and needed to be replaced to ensure reliable operation and mitigate any potential downtime risks. GTE was engaged integrate nine new Schneider Electric Altivar 950 VSDs into the hopper train control system, with one clear requirement: the upgraded system had to operate consistently with the existing hopper train, keeping changes to established operating practices to a minimum. These requirements shaped how the project was planned, tested and delivered, so that as much work as possible was completed before the team arrived on site.

GTE integrated nine Schneider Electric Altivar 950 VSDs with the hopper train PLC, upgrading the supporting control system infrastructure and completing a factory acceptance test (FAT) before mobilising to site. The approach was designed to keep operation consistent with the existing hopper train while making far better use of the communications the new drives offer.

Drive configuration and communication testing was completed during FAT, before the team travelled to site. This reduced the work required during the shutdown and let the available commissioning time be used more effectively.
The upgraded drives integrate with the existing hopper train control system while maintaining the hopper train's established operating requirements. Fuller use of fieldbus communication gives engineers direct access to drive information for diagnostics and fault-finding from a centralised workstation, a capability not previously available in this form.
Commissioning and testing were planned to manage risk to personnel and equipment. Testing was also used to confirm how the upgraded drives interact with the existing system, including the assessment of the cable reeler risk before the equipment was returned to service.
All nine VSDs were integrated into the control system on time, despite a tight commissioning window. Applying lessons learned from the previous upgrades, and retaining key personnel from these projects supported a more informed and efficient delivery.
The hopper train upgrade delivered a modern drive system that integrated with the existing control system and operates the way its teams expect. Clearer SCADA feedback and centralised engineering access gave both operations and maintenance personnel better visibility of drive status and diagnostics, supporting troubleshooting and delivering a faster mean time to repair. By leveraging their deep client knowledge and extensive brownfields expertise, GTE delivered all nine drives on time within a shortened shutdown window. GTE has also identified an opportunity to review the existing hopper train PLC code and standardise drive logic across the site, which would simplify future integration and maintenance. As Western Australia's largest independent system integrator, GTE Group combines control systems expertise, careful preparation, brownfields expertise, our state of the art test lab and a client-first approach to deliver upgrades that deliver ongoing benefits for our clients.
If you’re ready to hear more about how we can help your business operate safely and sustainably, get in touch with us today.
1300 921 590
admin@gtegroup.com.au
Level 2
109 St Georges Terrace
Perth, WA, 6000
Australia
PO Box 7099
Cloisters Arcade
Western Australia, 6850
Experience efficiency, reliability, and innovation with our expert engineering solutions.
Let’s take your operations to the next level—contact us today!
At GTE we transform complex engineering challenges into seamless solutions for your peace of mind.
© 2026 GTE Group Pty Ltd | All Rights Reserved | Powered by Design Studio Perth